Southern’s Tom Fanning to retire

December 18, 2023, 3:02PMNuclear News

Fanning

Tom Fanning, Southern Company board executive chairman and the man who helmed the firm during construction of the two new AP1000 reactors at Georgia’s Vogtle nuclear plant, will retire December 31, Southern has announced. His board seat will be filled by Chris Womack, who replaced Fanning as Southern’s president and chief executive officer earlier this year.

Elected by the Southern board in July 2010, Fanning became company president in August 2010 and assumed the additional responsibilities of chairman and CEO that December. During his more than 43 years with Southern, Fanning held executive roles across various business disciplines, including finance, strategy, international business development, and technology. As president, chairman, and CEO of Southern, he received numerous accolades, including being named one of the most influential leaders in the energy industry in the past 25 years.

ANS awarded Fanning a Presidential Citation at this year’s Annual Meeting in Indianapolis, Ind.

Further delays, higher cost for Vogtle project announced

February 17, 2023, 2:37PMNuclear News
Vogtle Unit 3, in January. (Photo: Georgia Power)

Already for the second time this year, Southern Company has announced a delay to the expected commercial operation of Unit 3 at the Vogtle nuclear plant’s two-unit construction site. In addition, a delay to Unit 4’s startup is also possible, Southern said.

Southern Company makes executive appointments

January 12, 2023, 7:00AMANS Nuclear Cafe
From left: Womack, Greene, and Sena. (Photos: Southern Company)

Southern Company has appointed Chris Womack chief operating officer effective immediately and president as of March 31. Tom Fanning will relinquish the role of president upon Womack's assumption of the role in March and is to assume the role of executive chairman of the board of directors.

Womack has served as president of Georgia Power since 2020 and chairman, president, and CEO since 2021. Prior to his current roles, he served as executive vice president and president of external affairs for Southern Company.

"Chris's leadership, vision, and integrity during his career with Southern Company have uniquely prepared him to guide Southern Company into a new era," said Fanning. "With our recent progress at Plant Vogtle and continued conversion of our operations towards net zero emissions, I believe that now is an ideal time to transition to new leadership."

The moves were announced by the company's board on January 5.

Vogtle project hit with new delay, higher cost

February 22, 2022, 9:30AMNuclear News
Fuel preparing to be unloaded outside of Vogtle-3 last month. (Photo: Georgia Power)

Commercial operation dates for the two new reactors under construction at the Vogtle nuclear plant have been pushed back yet again, adding to the project’s total cost, Southern Company announced last week. The Vogtle plant is near Waynesboro, Ga.

During its February 17 fourth-quarter earnings call, Southern reported that the projected start dates for both reactors were being extended by three to six months. Vogtle-3 is now expected to begin providing electricity to Georgians in the fourth quarter of 2022 or first quarter of 2023, with Vogtle-4 coming on line in the third or fourth quarter of 2023.

Georgia Power again pushes back Vogtle project start dates

October 25, 2021, 9:29AMNuclear News
Vogtle-4 containment as it appeared last month. Photo: Georgia Power

In what has become for nuclear advocates an all-too-familiar refrain, Georgia Power has made another revision to the Vogtle nuclear expansion project schedule. The company now predicts a Unit 3 in-service date in the third quarter of 2022 and a Unit 4 in-service date in the second quarter of 2023, representing a three-month shift for each unit.

Vogtle project suffers another setback

July 30, 2021, 12:00PMNuclear News
Vogtle Units 3 and 4, earlier this month. (Photo: Georgia Power)

Georgia Power yesterday announced that due to 'productivity challenges' and the need for 'additional time for testing and quality assurance,' it has revised the schedule for the Vogtle-3 and -4 nuclear expansion project. The new schedule pushes back the Unit 3 in-service date to the second quarter of 2022 and the Unit 4 date to the first quarter of 2023—a three-to-four-month shift for each unit.

Vogtle-3 startup delayed until January as costs increase

May 20, 2021, 7:15AMNuclear News

The commercial start date for Unit 3 at the Vogtle construction site near Waynesboro, Ga., has been pushed back to January of next year, adding some $48 million to the cost of the nuclear new-build project, according to Georgia Power and Southern Nuclear officials who were testifying at a May 18 hearing before the Georgia Public Service Commission.

Southern targets December for Vogtle-3 startup

May 3, 2021, 6:54AMANS Nuclear Cafe
Vogtle-3 turbine generator. Photo: Georgia Power

Southern Company is targeting December for placing Vogtle-3 in service, according to Tom Fanning, the company’s chairman, president, and chief executive officer, who spoke with financial analysts on April 29 in its first-quarter earnings call. “The site work plan now targets fuel load in the third quarter and late December 2021 in-service date for Unit 3,” Fanning said. “Of course, any delays could result in a first-quarter 2022 Unit 3 in-service date.”